Kiat Lim visits the Nou Mestalla with the men's first team
Valencia CF President Kiat Lim, the coaching staff and the men's first-team players have taken a close look at the progress of what will become the future home of the Valencia CF family
The installation of all auxiliary scaffolding for the tension ring cables has been completed, while work on the façade, stair towers and various interior areas continues to advance
Construction of the Nou Mestalla continues to make steady progress, with the project now entering the final stages of preparation before the lifting of the main roof structure, which will cover the 70,044 seats of Valencia CF’s future home.
In recent days, the installation of all auxiliary scaffolding required for the tension ring cable system has been completed. Significant progress has also been made on the protective structures within the stands ahead of the deployment of the radial cables, several of which have already been installed. At the same time, work has continued on the stadium façade, stair towers and a number of interior areas.
Latest news Ver todas
The goalkeeper gives his first interview since signing for Valencia CF
The coach previews that match against Real Betis
The new arrival talks about joining Valencia CF
Official Partners